Saturday, July 26, 2008

Day 10: 23 July 2008..Kitchen Cabinet Base

Framework of the kitchen base. Hai...pathetic small little kitchen







Day 8: 21 July 2008...Aircon Installation

Diana wanna arrange aircon installation on 18th, but because we couldnt decide on who to purchase the aircon from, we had to delay the installation. In the end, we decided to get from Winson (recommended by Diana). Guess that it would probably be better since Diana and Winson know each other and can communicate better on how and where to arrange the aircon n its trunking so that the trunking would not ruin the interior design.
We got the Mitsubishi Starmex System 4 inverter at $3800 from Winson. It's $160 more than Gain City, but Winson is willing to use the Armaflex insulation without additional cost, and he actuall makes 3 trips to our house.

-1st trip to look at our unit's layout n discuss with Diana on the running of the trunking
-2nd trip to install the trunking and pipings
-3rd trip to install the 4 aircon units and its compressor when reno is almost completed
Proof of using Armaflex
Pipes sticking out at the aircon ledge
Trunking in MasterBedroom
Aircon Unit to be positioned on top of the window
Bedroom 2
Trunking to Study Room
Living room Unit, to be positioned at Kitchen entrance


Day 4: 17 July 2008... Electrical Work

Hacking took 3 days, and electrician immediately took over and starts on doing up the electrical and lighting points. Electrician boss, Eddie is a really easy going and friendly guy. Finished his preliminary work in 2 days. Here's the results:

Lightings in Living Room & Study Room







Wednesday, July 23, 2008

Day 1: 14 July 08.....Hacking begins..

Hacking begins with just a small hole............
To a larger hole...........

Close up view.........
Side wall hacked........


Whole Kitchen entrance down...........


Look at the amount of debris created from the hacking..........


Kitchen & Study room all hacked..........


Study room......


Living & Study room through........


View from Kitchen


Final Look of the entire hacking......
How i wish the house looks this big without hacking......


Thursday, July 10, 2008

Finally....Renovation starts!

What a relief, our defects finally settled! We called Diana on 5 July, and yday, her workers had started laying cardboards on our floors to do protection before reno starts. Electrical work and air con trunking may be up today or tomorrow. Here's how it looks like: